The main challenge for this installation was the fact that we had just 1 week to complete in.
Fast track installations are key in commercial or industrial projects as every day the conference area was closed for refurbishment, the company was losing valuable income.
Planning and preparation were key and we set up three teams to work simultaneously in each room, keeping to our own targets throughout the week to ensure that we completed on time.
Large format porcelain tiles are not quick to install and in particular the mosaic border tile added a further complication. Clear and concise communication at every stage was essential to achieve our common goal.
The client was pleased with the precise timing and high quality of the installation.